Raleigh, NC ADA-Accessible Ramps & Utilities
Subcontract with Fred Smith Company
September 2019 – July 2020
0
Yards of Existing Granite Curb Reset
0
Retrofit Curb Ramps
0
Yards of Concrete Island
0
AT&T Manholes Adjusted or Replaced
0
Manholes Adjusted or Replaced
0
ADA-accessible Ramps
0
Water Valves Adjusted or Replaced
When the project began in September 2019, utility work was done during the nighttime to minimize traffic disruptions. Then, work paused from December 2019 to January 2020 for the concrete crew to complete the ramps. The project finished in July 2020 following a month-long pause due to COVID-19 in May.